Main Content
Link to Michigan State University Home Page
MSU Construction IPF Home
  • Construction Home
  • Projects
  • Detours
  • Listserv
  • Construction Junctions

Recently Updated

May 9, 2013 Meeting Agenda
April 11, 2013 Meeting Agenda: Ice Cream Cones and Construction Zones
March 14, 2013 Meeting Agenda
February 14, 2013 Meeting Agenda
January 10, 2013 Meeting Agenda
  • Construction Home
  •  » Construction Junctions
  •  » Archived Meeting Materials
  •  » April 9, 2009 Meeting Agenda
  •  » April 9, 2009 Meeting Minutes

April 9, 2009 Meeting Minutes

Construction Junction

Construction Planning and Progress Meeting

B104 Wells Hall

April 9, 2009

Overview:
Construction Junctions are the Physical Plant’s monthly public meeting designed to update/inform the public of various projects currently in design, nearing construction and under construction. Agenda items included:

  • Karen Zelt
    • Board of Trustees Action

  • Jeff Kasdorf

    • Emmons Hall Renovation

  • Mark Haslam

    • Life Science Addition No. 1

  • Andy Linebaugh

    • The New Farm Lane — Underpasses Construction

    • Wilson/Birch Roads — Steam Distribution and Road Reconstruction

  • Kevin Durkin

    • Wharton Center — Addition No. 1 and Renovations

  • Chris Burns
    • Surplus and Recycling Center
    • Secchia Center — MSU College of Human Medicine Grand Rapids

 Project Notes/Questions

Emmons Hall Renovation

  • Located in southeast corner of Brody Complex
  • $15 million budget
  • Building is more than 50 years old
  • Project highlights:
    • Replacing roof
    • Replacing freight elevator with passenger elevator
    • Converting to hot water heating system
    • Installing new storm water piping
    • Ventilating public places
    • Adding smoke detector and sprinkler system
    • Most dramatic changes in public lounges include more natural light, a glass curtain wall, double-height lounge on the first floor, community kitchen, laundry, social areas, study areas
    • Improving residence hall apartments for staff
    • Adding caucus room on the fourth floor
    • Heated walks, automated doors, internal ramping system, barrier-free parking
    • Corridors are getting new finishes — adding natural light, painting and new finishes and circuits in rooms
  • Be(ing) Spartan Green:
    • Natural light in corridors, public lounges
    • Renovating bathrooms — new plumbing and new fixtures

 Life Science Addition No. 1

  • College of Nursing — northern wing of Life Science building
  • Four-story addition to nursing — add classrooms and gathering space hopefully with Sparty’s convenience store
  • Goal is to double the enrollment of the College of Nursing
  • Adding undergraduate teaching space which will also be used for community outreach
  • Upper levels include flexible floorplate (offices and grad research areas will all have totally flexible walls and furniture)
  • Will create dramatic presence for the College of Nursing
  • Tranquility garden — research shows there are many benefits of this amenity
  • Concept to put classroom and public spaces on first floor
  • Third and fourth floors will include offices, research modules. The center offices will be essentially transparent with surrounding workstations using daytime lighting
  • Be(ing) Spartan Green
    • Going for LEED (Leadership in Energy and Environmental Design) silver certification
Q: Proposed construction schedule?
A: Break ground late fall 2010. Will be occupied within one year.
Q: Additional parking?
A: Only additional parking as part of project is a turn-around at the main west entrance for ADA (Americans with Disabilities Act) compliance (think of Bogue Street median parking), but that is currently not funded, so may not be in end project.

The New Farm Lane — Underpasses Construction 

  • Work continues — favorable weather helping progress
  • Started on electrical and communication ducts and manholes
  • Bolt replacement work required on the CN (northernmost) bridge — currently hanging conduit supports
  • Working on internals for north pump station
  • Actual pump house for the north station is blocked out
  • Continue to pour retaining walls
  • Finished up minor work on CSX (southernmost) bridge
  • Asphalt plant opened early — allowing asphalt deck to be laid on north bridge
  • In two to three weeks train traffic will be permanently switched to north bridge — then will finish south side
  • Installing new well main section under Service Road
Q: When will you close off parking for Food Safety and Toxicology?
A: Required to leave drive open at all times. Contractor has requested to close on select weekends — looking at potential weekends
Q: Ready for fall?
A: There were challenges this winter, putting us currently a bit behind, but it is still pretty early to project an opening date. It will definitely open this fall, not sure when in the fall.

Wilson/Birch Roads — Steam Distribution and Road Reconstruction

  • Sheet piling — dig excavation through for sheet piling
  • Digging vault 337
  • Traffic shifted April 1: Closed Wilson Road from westernmost Cherry Lane entrance to Harrison Road
  • Wilson/Birch detours will be lifted during move-out period, May 1-10
  • After move out, the remaining portion of Wilson Road will be closed throughout most of the summer

 Wharton Center — Addition No. 1 and Renovations

  • Approximately 70 percent complete
  • Glazing on the front is almost finished and the cut out is in place for signage
  • Donor lounge areas close to having finishes done
  • Ticketing area — planning on moving in mid-June
  • Fourth-floor mechanical room — all equipment is in
  • Be(ing) Spartan Green:
  • Although this is not a LEED project, we are using a lot of LEED guidelines (50 percent of waste off the site is recycled, using recycled material in countertops, low-flow fixtures in restrooms, borrowed light in office spaces and outside views, bamboo (a rapidly renewable material) floor in patron lounge, etc.)

MSU Surplus Store and Recycling Facility

  • On schedule even with snow slowing down progress a bit
  • In process on finishing it out
  • Building to be open by end of June; will be fully functional for fall 2009
  • Most of exterior skin has been erected — finishing in the next 30 days 

Secchia Center — MSU College of Human Medicine Grand Rapids

  • Finishing closing up the building
  • About 50 percent of the cladding on the building
  • Started the windows — will take about two months to finish windows
  • The building should be enclosed by mid-summer

Notice:

March 4, 2013— Infrastructure Planning and Facilities is the new unit under the governance of Ron Flinn, recently appointed Vice President for Strategic Infrastructure Planning and Facilities. In upcoming months, this website will change to reflect the name and structure of the new unit. For more information on the reorganization, visit ipf.msu.edu/neworganization.


 

  • Construction Home
  • Projects
  • Detours
  • Listserv
  • Construction Junctions
©2013 Michigan State University Board of Trustees.
MSU is an affirmative-action, equal-opportunity employer.
East Lansing MI 48824