Brody Complex Utilities Phase III
Wells Hall Addition/Morrill Hall Replacement
FRIB/Plant Science Utility Relocation Phase I
Plant Sciences Expansion
Eli and Edythe Broad Art Museum
Brody Hall Renovation
Emmons Hall Renovation
  • Construction Home
  •  » Construction Junctions
  •  » Archived Meeting Materials
  •  » November 11, 2010 Meeting Agenda
  •  » November 11, 2010 Meeting Minutes

November 11, 2010 Meeting Minutes

Construction Junction

Construction Planning and Progress Meeting
118 Eppley Center
November 11, 2010 

Overview: Construction Junctions are the Physical Plant’s monthly public meeting designed to update/inform the public of various projects currently in design, nearing construction and under construction. Agenda items included:

  • Will Whelton
    • Board of Trustees
  • Jason Vallance
    • Commissioning efforts across campus
  • Adam Lawver
    • Campus snow plan 
  • Chris Thronson
    • Facility for Rare Isotope Beams Utility Relocation Phase I
    • Plant Science Expansion
  • Ken Dawson
    • Emmons Hall Renovation
  • Josh Pittsley
    • Brody Hall Renovation
  • Erin Bowdell
    • Eli and Edythe Broad Art Museum
  • Ken Gottschalk
    • Wells Hall Addition

Special presentations:

Commissioning efforts across campus
 
  • Department established in summer 2007
    • Reports to Gus Gosselin, Director of Building Services
  • Department mission
    • Optimize the operation of energy-consuming equipment 
    • Address building performing issues
    • We ensure we “get what we are paying for” on new construction projects
    • Sustain building performance
    • Increase occupant comfort
  • New construction commissioning
    • Verify design, construction and equipment of buildings as per MSU requirements 
    • Design: a building is cheaper to fix on paper versus once it has been built
    • Construction: verify correct equipment delivery, installation and start-up activities
    • Hand-off: verify that all documents received reach all involved parties
  • Existing building commissioning
    • Driving force for department creation – meet campus energy goals
    • 114 main campus buildings slated for existing building commissioning 
    • 77 general fund buildings -  Five years
    • 32 Residential and Hospitality Services buildings – 10 years
    • Five athletics buildings – Five years
    • Verification through documentation, collection, system evaluation, and non-intrusive low-cost modifications to ensure building is operation to building requirements 
  • Five-step process
    • Building selection/prioritization
    • Documentation and bid pack creation
    • System evaluation
    • Implementation
    • Final reporting (follow-up testing for results)
  • Current projects
    • Anthony Hall
    • Built in 1957
    • Renovated in 1997
    • 350,000 square feet
    • Completely modernized with state-of-the-art labs, etc.
    • Team consists of commissioning teams and two contracted firms
      • Peter Basso and Associates
      • Aerodynamics Inspecting Company
  • What to expect
    • Testing/adjusting/balancing activities
    • Steam trap survey
    • Vibration checks on rotating equipment
    • Occupant survey process
    • Implementation of proposed repairs
  • Upcoming schedule
    • Food Stores
    • Oyer Speech and Hearing Building
    • Spartan Stadium
    • Vet Med Building
Campus snow plan
  • Be snow safe!
    • Drive carefully
    • Dress warmly
    • Wear sensible shoes
    • Watch where you are walking
    • Check the forecast before you head outside
  • Safety
    • Please do not walk out in front of snow plows; they are very difficult to stop
    • Make eye contact with the driver before crossing
  • Salting
    • Call 355-7750 for help with icy spots
    • Please do not over salt; it can cause damage to turf
    • Remember to salt when you see an icy spot
  • Sidewalks
    • Please do not park so that parts of your vehicle so that parts overhang the sidewalk
  • Snow stacking
    • Please do not park in un-plowed areas
    • Parking in snow stacking locations will result in a ticket
    • Approximately 20,000 parking spaces on campus must be plowed each morning before 8 a.m.
  • Residence hall parking loops
    • Closed from 2 a.m. to 6 a.m.
  • Bikes
    • Please do not chain bikes to signs, railings, etc.
    • This makes it very difficult to plow and is not allowed on campus
  • Contact
    • For more information, please visit landscapeservices.msu.edu and click on the snow removal section.
    • Email snowplan@pplant.msu.edu 
    • Call 355-7750 to report any icy spots or request help

Project updates:

Facility for Rare Isotope Beams Utility Relocation Phase I

  • Relocating utilities for the FRIB tunnel to be installed on the south side of the Cyclotron
    • Chilled water has been tied in recently
  • Utilities for the high-bay are being installed on the east side of the building
  • Storm and sanitary sewers almost complete on the south side of the building
Plant Sciences Expansion
  • Two primary activities
    • Erection of structural steel
    • Installation of concrete
  • First floor will be complete by the end of this week
  • Waterproofing is happening at foundation level
  • Concrete in basement being installed for mechanics areas
  • Lane closure on Wilson Road still in effect
    • Will be removed for home football game activities
Emmons Hall Renovation 
  • Emmons entrance of Brody is closed until 2011
  • Building must be enclosed before winter for heating purposes
    • Heat is scheduled to turn on next week
  • Framing for glass has been installed
    • Glass is currently being installed
  • Concrete is being poured as much as possible before winter
  • Stairwells are still open areas 
  • Roof has been ballasted; now waterproofed and dry
  • Penthouse is roofed on top, siding is last to go in
  • New handicap accessible ramps are being installed in place of some interior stairs 
Brody Hall Renovation
  • Most of the landscaping is done and the exterior is basically complete
  • Office area on the first floor has complete plasterwork and will be painted soon
  • Most of the first floor framing has been completed
  • 85 percent complete of overhead mechanical work is complete
  • Bathrooms are complete with masonry and paint, being tiled currently
  • The Sparty’s coffee shop will be located near the front entrance of the building
    • Self-service coolers have been installed
Eli and Edythe Broad Art Museum
  • Pouring concrete deck
    • A tremendous amount of steel being used for this structure
  • More of the site around the building will be able to be used
  • Concrete poured on first floor deck
    • Workers used platforms to spread weight and level concrete
  • Forms for interior walls are going up
    • Plywood formwork will be used as a mold for the concrete and leave imprints; this idea is directly from the architect’s plan
  • Non-architectural wall uses massive steel reinforcement
  • East Circle Drive will continue to be closed until December 2011
  • Snow melt is being installed as well as an accessible ramp in front of Student Services Building north entrance
    • The entrance will reopen in January 2011
Wells Hall Addition
  • A temporary sidewalk has been constructed on the west side of Red Cedar Road
    • Trying to keep pedestrians out of the road
  • Exterior walls on B-wing are down and work is ongoing
  • The floor will be demolished and HVAC systems replaced 
  • Demolition is about 85 percent complete now
  • Digging in rooms to install micro piles and caps next week 
  • Micro piles are used to support the steel structure of the building
    • Steel is going up in mid-December
    • The park side of the building and the B-wing (including the coffee shop) will be live as of fall 2011
 

 

Notice:

March 4, 2013— Infrastructure Planning and Facilities is the new unit under the governance of Ron Flinn, recently appointed Vice President for Strategic Infrastructure Planning and Facilities. In upcoming months, this website will change to reflect the name and structure of the new unit. For more information on the reorganization, visit ipf.msu.edu/neworganization.


 

  • Construction Home