Description: This is a partial package to the Facility for Rare Isotope Beams (FRIB) project that is scheduled to start in 2013. Prior to the start of FRIB, the university must relocate utilities to support it. This project coordinates the FRIB utility relocation work (Phase I) with the Plant and Soil Sciences Building construction site work, thus eliminating construction coordination conflicts (timing and staging) between the two projects. The project also includes the relocation of the chilled water, natural gas, sanitary and storm sewers, domestic water, communication and electrical distribution.
Additionally, the coordination of these two projects will remove the need to shutdown Wilson Road for four years in a row and provides the least amount of disruption to campus operations.
Timeline: Construction will begin in May 2010 and end in mid-November 2010.
Impacts to pedestrians, bikers, motorists:
Questions, comments, concerns?
Design Representative: Scott Gardner, mgardner@pplant.msu.edu, (517) 432-0782
Construction Representative: Chris Burns, cburns@pplant.msu.edu, (517) 353-8619