Main Content
Link to Michigan State University Home Page
MSU Construction IPF Home
  • Construction Home
  • Projects
  • Detours
  • Listserv
  • Construction Junctions

Project Status

  • Planning/Design
  • Construction
  • Archived
  • Construction Home
  •  » Projects
  •  » Michigan State Police Post Demolition
  •  » Michigan State Police Post Demolition Information

Michigan State Police Post Demolition Information

  • Pre-demolition:
    • March: Construction fencing installed along the east side of the site.
    • April - June: 
      • April 1 - MSU officially reclaimed the site from the Michigan State Police.
      • The Physical Plant’s Landscape Services department will install white plastic tree fencing on site, which is strictly used for tree protection during demolition.
    • April – June: Asbestos abatement – a standard step in nearly all other campus renovation projects – is currently being performed. It will be carried out in an Environmental Protection Agency (EPA)-approved method, with a third-party air-monitoring consultant on-site; The Physical Plant and Environmental Health and Safety (EHS) will also partner to ensure MSU/EPA standards are enforced.
  • Demolition:
    • April 9: Demolition begins
    • Site Access Requirements: Through the parking lot north of the site to Kalamazoo Street
    • Demolition process: 
      • The contractors will be working from east to west taking down the buildings.
    • Safety: Campus police will patrol the area.
    • Watch speed: On Kalamazoo, large trucks will be exiting the site and heading west on Kalamazoo Street to U.S. 127
    • Aug. 17: Completion date. All buildings will be removed and the contractor will be gone.
  • Materials will be reused/recycled:
    • The project has target goal to recycle/reuse at least 75 percent of building materials from the site.
  • Minimizing impacts:
    • Tree protection: There will be surgical demolition on site to protect trees. 
    • Dust control: The contractor will control dust with water during demolition. Dust will continue to be controlled until the site is returned to the university.
    • Hydro-seeding/mulching: This will stabilize the soil to eliminate dust and grow grass.
    • Soil-erosion and storm water control: Soil-erosion permit through the City of East Lansing has been obtained. Also the Michigan Department of Environmental Quality is aware of this project.
  • Sights, sounds, smells:
    • No explosives will be used to demolish the buildings; excavators will be used instead. 
    • Dust-control measures will be in place prior to and during demolition.
    • Demolition is not expected to be very loud; the demolition equipment will be the loudest sounds (back-up beeps, excavators, etc.)
  • Hours of demolition work:
    • 7:30 a.m. to 5 p.m.
  • General contractor in charge of project: Pitsch Companies
  • Post-demolition site improvements:
    • The site will become a parking lot. 
    • Site restoration will begin as buildings are demolished and will run through September 2012, including grading, grass seeding, mulching and removing tree protection.
    • Construction fencing will remain once project is complete.
    • Reduction in rainwater runoff from the site is a goal, so the amount of catch basin inlets will be reduced and monitored.
    • MSU will be responsible for the site after completion of the project.
    • New drainage will not be added, the existing drainage will remain.
    • Three new gates will be added for special events. Both will be at the north end of the lot.
  • Construction Home
  • Projects
  • Detours
  • Listserv
  • Construction Junctions
©2013 Michigan State University Board of Trustees.
MSU is an affirmative-action, equal-opportunity employer.
East Lansing MI 48824